Backbone Link Target Production Date

Backbone Circuit Finish
Fiber Implementation Kickoff
2/20/2008
Order & Delivery of Optical Gear
6/30/2008
Fiber/Optical Implementation
11/14/2008

Kansas City to Columbia Fiber Route

11/14/2008

Kansas City Metro Ring

11/14/2008

Columbia to St Louis Fiber Route

11/14/2008

St Louis Metro Ring

11/14/2008

St Louis to Stoutland Fiber Route

12/1/2008

Rolla Metro Ring

12/1/2008

Stoutland to Columbia Fiber Route

12/1/2008

Jefferson City Metro Ring

12/1/2008

Springfield to Kansas City Fiber Route

12/12/2008

EMS Implementation

10/20/2008

Optical Testing and Provisioning

12/23/2008
Collocation Facility Moves  

Jefferson City to Stoutland

12/8/2008

UMKC to 1102 Grand

2/1/2009

UMSL to 900Walnut

3/1/2009
Routing Implementation  

Order/Receive New Equipment

5/1/2008

MOREnet Core Routers

3/10/2009

ICN Core Router Installation

3/29/2009
Backbone Turn-Ups  

MOREnet 10Gig Backbone

12/28/2008

ICN 10Gig Backbone

3/22/2009

GPN 10Gig Circuit

5/1/2009

RHC 2Gig Backbone

1/11/2009
Agreements  

Develop ICN Management MOU

9/5/2008

Develop Hands/Eyes Agreement

12/12/2008